Case study: 16-storey commercial tower facade, Mumbai

38,000 sqft of unitised curtain wall. Wind-zone qualified to +2.0 kPa. 142-day timeline from PO to RFO. Concurrent with 10+ other live projects.

  • 38,000 sqft of facade glazing
  • 16 storeys + double-height ground lobby
  • Unitised curtain-wall system — factory-finished modules
  • 142 days PO-to-handover (the developer's SLA was 180)
Commercial tower with full glass curtain wall in Mumbai — representative project visualisation

Project brief

A speculative-build commercial tower in BKC. Developer required a Grade-A facade qualifying for IGBC Platinum, with a 30% better solar-heat-gain coefficient than the city baseline and capable of withstanding Mumbai's coastal wind exposure (+1.8 kPa face load, ASTM B117 1,000 h salt-spray).

The tendered scope was for a stick-built system. We counter-proposed a unitised curtain-wall approach: every floor's glazing arrives as 1.5 × 4 m pre-assembled modules, lifted by tower crane, hooked onto pre-installed brackets. The proposal saved 32 days of erection time and reduced site labour by 40%.

System spec

SpecValueWhy
SystemUnitised curtain wall, 150 mm mullion depthCarries 4-storey wind-load + dead load with cantilever capacity
Glass8 mm HT + 16 mm argon spacer + 8 mm Saint-Gobain Cool-Lite SKN 154 IISHGC 0.27, U-value 1.4 W/m²K — exceeds IGBC Platinum requirement
CoatingQualicoat Class 2 Seaside, RAL 9007 grey aluminiumCoastal-grade for Mumbai salinity
BracketsM16 SS316 + GI cast-in plates per floorStainless inside the building envelope to prevent staining
SealantDow Corning DC-995 structural + DC-791 weather25-year proven life in Mumbai coastal exposure

Wind-load + water-tightness sign-off

We engaged the structural consultant's preferred third-party lab (CBRI Roorkee) for the project-specific sign-off. Two full-floor mock-ups (3 m × 12 m) were assembled at the lab and tested for:

  • Wind load: +2.0 kPa, -2.0 kPa, no failure (15% margin over Mumbai design wind)
  • Water-tightness: EN 12208 Class 9A at 600 Pa — no penetration over 30 min
  • Air permeability: EN 12207 Class 4 — < 0.5 m³/h·m
  • Inter-storey drift: ±25 mm at 1/200 storey height — no glass damage

Timeline

PhaseDaysOutcome
Design + drawings + structural sign-offDays 0–28PEB-coordinated GAD + 110 shop drawings approved
Mock-up & lab certificationDays 29–48CBRI test reports issued; developer release
Production batch 1 (floors 1–4)Days 49–76160 unitised modules built, packed, shipped
On-site erection of batch 1Days 67–96Concurrent with later batches in production
Production batches 2–4 (floors 5–16)Days 77–118480 modules + ground-lobby
On-site erection of batches 2–4Days 97–134Full envelope dry
Sealant cure + RFO inspectionDays 135–142IGBC sign-off + developer handover
Total142 daysvs. tendered 180 days

What we learned

Frequently asked questions

Do you take on facade-engineering responsibility or only fabrication?

Both, on B2B projects. On this project we took full design-build responsibility including structural coordination with the developer's PEB consultant, sealant warranty (25 years via Dow Corning), and IGBC documentation.

What is the GST treatment for a project of this scale?

GST @ 18% is charged on the basic value. For B2B (registered) customers, the full GST is available as input-tax-credit, making the effective cost equal to basic value + transport. See our GST policy.

Mumbai is > 700 km from Hyderabad — does free transport apply?

Yes — Mumbai is 711 km from our Hyderabad factory, within the 1,000 km radius, and the order value comfortably exceeds the ₹15 L threshold. Full transport was free.

Do you carry workmen's compensation insurance for high-rise erection?

Yes, plus a project-specific Public Liability + All-Risks construction policy taken at the start of every B2B project > ₹50 L. Schedule shared with the developer at PO stage.

How do you handle service after handover?

A dedicated maintenance manual is handed over including BMU operating instructions for facade cleaning. Annual structural & sealant inspections optional under our 5-year AMC.

Ready to lock down a final binding quote?

WoodenMax engineers visit free within 48 hours, measure on site, and share a locked PDF quote with GST & transport pre-confirmed.

Book free site visit →

GST 18% extra • Free transport on ₹15L+ orders ≤ 1,000 km from Hyderabad • policy